Quoth EricKei
View Post
Of course, my boss and the guy that is in charge of the server room realized back in December that it was going to be a problem and started requesting a third AC unit be installed. And, as one should expect my company didn't want to pay for a third unit and kept putting off the request. It wasn't until the 4th weekend of having to run around shutting everything off that we finally got approval to put in another unit. Now they have to get special permits to install it. From the looks of it, we won't get the thing installed until the fall, when it's not needed. Did I mention that in early 2010 we're taking over a second server room that has its own AC units and therefore the whole thing will be moot? Thankfully my boss has enough foresight to see that we'll eventually fill up both rooms and will need the extra unit anyways in a couple years so he's still pushing ahead with getting the new unit.